Sweaney is back at Paramount Citrus plant in Delano, Ca. to help construct a 20,000 square feet 2 story addition to the 41,000 sf office building. We built in 2012 we are longstanding partners with Younglove Construction Group & will be providing the metal studs, drywall & EIFS finish at the exterior as well.
![4/15/2014-First day on site](https://sweaneyinc.com/wp-content/uploads/2015/06/IMG_1598-1024x764-1024x764.jpg)
![4/25/2014-Making great progress with the exterior framing](https://sweaneyinc.com/wp-content/uploads/2015/06/IMG_1678-1024x764-1024x764.jpg)
![4/29/2014-Stairwell framing completed](https://sweaneyinc.com/wp-content/uploads/2015/06/IMG_1679-1024x764-1024x764.jpg)
![4/27/2014-Began top out drywall before overhead ductwork can be installed](https://sweaneyinc.com/wp-content/uploads/2015/06/IMG_1776-1024x764-1024x764.jpg)
![We installed a 6″ coreshaft system at the elevator shaft](https://sweaneyinc.com/wp-content/uploads/2015/06/IMG_1914-1024x764-1024x764.jpg)
![We installed tile backer board under the ceramic tile in the restrooms](https://sweaneyinc.com/wp-content/uploads/2015/06/IMG_1907-1024x764-1024x764.jpg)
![We are appling exterior gyp sheathing as the substrate to apply the EIFS](https://sweaneyinc.com/wp-content/uploads/2015/06/DG1.jpg)